Connect a power plant owned by a consumer

Documents required for Connection

  1. The qualification certificate of the executing company issued by the New and Renewable Energy Authority..

  2. A contract between the executing company and the project owner..

  3. A copy of the national ID card, tax card or commercial register of the project owner.

  4. A copy of the tax card and commercial register of the executing company.

  5. A photo of an electrical connection receipt.

  6. A photo of an electrical connection receipt.

  7. Technical specifications of the project and a copy of the catalogs.

  8. Test certificates for the project components.

  9. Electrical diagram of the project and the proposed connection point.

  10. An acknowledgment of not violating the Unified Building Law and endure civil and criminal liability for violating the building requirements/conditions for this project.